In construction disputes many Extension of Time (EOT) claims fail not because the delaying events lack merit but because the analysis is technically flawed or unsupported by evidence.
A strong delay claim requires more than simply showing that delay events occurred. It requires a detailed analysis supported by contemporaneous records, appropriate delay analysis methodology and a clear demonstrable link between cause and effect.
The table below highlights seven of the most common mistakes observed in EOT claims, presented in the form of Do’s and Don’ts Matrix.
| Delay Analysis: Key Do’s and Don’ts Matrix | ||
| Topic | DO’s | DON’Ts |
|---|---|---|
| 1. Baseline Programme |
|
|
| 2. As-Built Records |
|
|
| 3. Critical Path Impact |
|
|
| 4. Concurrency |
|
|
| 5. Selection of Methodology |
|
|
| 6. Application of Method |
|
|
| 7. Cause and Effect |
|
|
A strong delay claim is not built on the volume of documents or on massive arguments, but on logic, sound methodology and technical reliability.
To summarise the above, a defensible delay analysis requires:
- A reliable and approved baseline
- Robust contemporaneous as-built records
- Clear demonstration of impact on the critical path
- An appropriate and properly applied methodology
- A clear demonstrable cause-and-effect narrative and link
When these elements are present, a delay claim becomes credible and robust. When they are absent, even a valid claim can be challenged or rejected entirely.
The strength of a delay claim does not rely on the story told but on the evidence and methodology that support it.